If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

What causes the output work of a machine to be less than the input work?????
Find the missing dimension. Round your answer to the nearest tenth. Please help me answer this problem. :) thanks.
A primary reason for Japan’s involvement in the Sino-Japanese War and the Russo-Japanese War was to... 1)acquire natural resources in Manchuria and Ko
Fiscal policy is the government s approach to?
sailfish are the fastest fish in the world they can swim 68 miles hour estimate how far sailfish can swim in 3 hours
All of the following make up the big three credit reporting agencies EXCEPT: A: Equifax B: TransUnion C: Experian D: Federal Reserve
The Roman Constitution called for the government to be made up of the senate, the legislative assemblies, and the executive magistrates. This is an example of
1. Identify two techniques that the cartoonist used and explain what ideas are conveyed through each technique? 2. What is the message of the cartoon?
What does 5×17×12×1300?
What is the nitrogen cycle?