Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

What is the missing term? (10x – 4x^2) – (7x + ?) = 3x – 6x^2 -10x^2 -2x^2 -x^2 2x^2
Will soapy water evaporate faster than water
Factor. 2w3+4w2–9w–18
Police matched the DNA from a strand of hair taken at the scene to catch the burglar. They used _____.
What is an undifferentiated cell whose “job” within the organism is yet to be determined
What is a prejudice? a. an oversimplified or inaccurate assumption shared by a group of people b. a situation in which an employee can take unfair advantage of
What is one way to find the total cost of a jacket for $55.80 with a sales tax of 2.7%
could someone help me with this? ty
Please help. I will give brainliest(:
"how do command-and-control policies differ from incentive systems?"